ACADEMY · FREE MODULE 10 OF 11

M10 · Kaizen Events

7 min video with captions · one-page job aid · short quiz

Job aid

One process. One week. Every change measured.

A kaizen event is a short, focused team effort (3–5 days) to improve one process. The people who do the work make the changes. It isn't a meeting, and it isn't a one-person project.

1 Plan it: the event card

Field Write
Scope Where the process starts and where it ends
Team Sponsor · facilitator · team lead · people who do the work · approvers (e.g. safety, quality)
Baseline Measured from real data, not memory (how many events, over what period)
Target A number
Dates The event days and the report-out
Days Day 1 Day 2 Day 3 Day 4 Day 5
3 Walk, measure, sort Find waste, test changes Measure, standardize, report out
4 Walk and measure Find waste, pick ideas Test on the real work Measure, standardize, report out
5 Walk and measure Find waste Pick ideas, first tests Test again on the real work Measure, standardize, report out

2 Run it: try, measure, keep or drop. Give every change its own before and after: Change · before · after · keep / adjust / drop.

3 Follow it through. Report out: baseline · changes · results (honest about any gap) · open items. Then the action plan:

What Owner Due Status
One open item per row A named person Within 30 days Open · done

Anything due after 30 days gets a 30-day milestone row.

Watch out for: scope too wide · no baseline · changes not tested on the real work · open items with no owner · declaring victory on the last day.

Examples

Industry Event Baseline → result (target) Open items
✈ Airline MRO 4 days, AOG parts response 4.2 → 2.3 h over 6 events (2.0 h) Direct ordering path · stores lead · 30 days
📦 Logistics 4 days, dock-to-stock 28 → 9.5 h over 15 trailers (< 8 h) ASN agreement · inbound manager · 60 days; review held and draft sent in 30
⚙ Manufacturing 3-day SMED, press changeover 95 → 38 min (≤ 30 min) Quick-release clamps · maintenance · 30 days; die cart · engineering · 45 days (design approved in 30)
✚ Healthcare 5 days, OR turnover 48 → 33 min over 12 turnovers (30 min) Extra instrument tray set · theatre manager · 30 days
🏦 Banking/Services 3 days, card disputes 12 → 7 days in the trial; 4 handoffs → one case owner (supplemental example)

All examples are fictional.


Page 2 · Tabletop simulation kit (90 minutes, 4–6 people)

The process (invented for practice): an office supply request. Read it aloud; no props needed.

Step Time per request
1 Fill in a paper request form 6 min
2 Wait in the manager's in-tray 2 days
3 Manager signs 2 min
4 Wait for the weekly order run 3 days
5 Admin re-types the request into the ordering system 8 min
6 Goods arrive; requester is emailed to collect 1 day
Baseline about 6 days

Run it

Time Activity
10 min Read the process; agree scope (form filled in → goods collected), roles and the baseline
15 min Find waste: mark each step value-adding, waste or required
45 min Three rounds of try, measure, keep or drop: each round, change one thing, recalculate the time, decide
10 min Report out: before → after, honest gap
10 min Write the 30-day action plan

Facilitator checklist: ☐ scope stated with start and end ☐ baseline written down ☐ three changes tested, one at a time ☐ before and after recorded for each ☐ every open item has an owner and a date within 30 days.

Quiz

Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.

Pass mark: 5 of 6 questions. Q6 counts as correct at 5 of 6 rubric points.

Q1 · Airline MRO · The baseline and the team

Scenario: A fictional maintenance base is planning a four-day event on the AOG parts response (AOG: "aircraft on ground", an aircraft that can't fly until a part arrives).

Question: Which baseline belongs in the plan, and why is a quality engineer on the team?

Q2 · Logistics · Which change cut the most?

Scenario: A fictional distribution center ran a four-day event on dock-to-stock (from a trailer being unloaded to goods ready for picking), baseline 28 h. Three changes were tested: labels printed from the ASN (the supplier's advance shipping notice): labeling 0.25 h → 0 · check and label in one step: a 12 h wait → 0 · hourly put-away runs: an 8 h wait → 1.75 h.

Question: Which change cut the most time?

Q3 · Manufacturing · Internal or external?

Scenario: In a fictional SMED event (a method to cut changeover time), the team sorts a stamping press's changeover tasks into internal (only possible while the press is stopped) and external (can be done while it's still running).

Question: Which task can move to external setup, and which must stay internal?

Q4 · Healthcare · A complete action-plan line

Scenario: A fictional surgical suite's event cut OR (operating room) turnover from 48 to 33 minutes over 12 trial turnovers, against a 30-minute target. The team writes its action plan.

Question: Which line is complete?

Q5 · Banking/Services · Transfer question

Scenario: A fictional bank runs a three-day event on card disputes (when a customer challenges a card payment). Today a dispute takes 12 days from the customer's claim to resolution and passes through 4 handoffs (moves from one team to another). The trial uses a single case owner and standard evidence requests.

Question: Which measure is the right before and after?

Q6 · Planning exercise (learner's choice)

Task: Plan a 3–5 day event for a process you know, or for this one: new starters wait an average of 9 working days for a laptop and system access; the target is 2 days. Fill in the event card, write the agenda by day, and write a 30-day action plan for two open items.

All examples are fictional.