6 min video with captions · one-page job aid · short quiz
Job aid
The best way so far, written down
Standard work is the current best way to do a job, written by the people who do it, so anyone can do it the same way. It's the baseline you improve from, not a cage.
Element
Ask
How
Takt
What pace does demand set?
Takt = available working time ÷ demand (same units). Compare each cycle time with takt on a bar chart
Sequence
What are the steps, key points and reasons?
5–10 steps in order; each with a key point (how) and a reason (why); required checks and sign-offs are steps
Standard WIP
How much may wait here?
A small, fixed amount in a marked place, so a pile-up shows at once
Bars vs takt: a bar over the line is the bottleneck (work piles up behind it); a bar far under it is idle time. Move work from tall bars to short ones until each is under takt. Minimum people = total work content ÷ takt, rounded up.
Instruction template
#
Step
Key point (how)
Reason (why)
Picture
1
What to do, starting with a verb
The one thing that makes it right
Safety, quality or ease
Optional
The first-try test: give the instruction to someone new. Can they follow it alone, with no help and no errors, first time? If not, fix the instruction, not the person. When the work improves, update the standard (v1 → v2).
Watch out for: confusing takt with cycle time · writing the standard without the people who do the work · leaving required checks out · treating the standard as fixed forever.
Examples
Industry
Takt
Cycle vs takt
Sequence and WIP
✈ Airline MRO
450 min ÷ 9 aircraft = 50 min
58 min per check; staging the parts kit cuts rectification 20 → 12 min: 50 min. Records and release untouched
9-step wheel and brake change (duplicate inspection kept) · 5-item handover · WIP: 1 parts kit, next aircraft only
✚ Healthcare
480 min ÷ 32 patients = 15 min
9 + 9 = 18 min room cycle (≈ 96 min over per session); room reset cuts turnover to 6: 15 min
6-step room reset · SBAR bedside handoff · WIP: 1 patient per room. Supports clinical judgement, never overrides it
⚙ Manufacturing
54,000 s ÷ 480 units = 112.5 s
S2 130 s over takt; moving the 20 s label task to S3 puts every station under. 418 ÷ 112.5 = 3.7 → 4 operators
8-step S3 standard · WIP: 1 unit per marked square
📦 Logistics
25,200 s ÷ 300 orders = 84 s per station
Observed 96 s: 12 s over takt
6-step picture instruction · WIP: max 2 totes per station (supplemental example)
🏦 Banking/Services
390 min ÷ 40 cases per reviewer ≈ 9.75 min per case
n/a
A standard checklist sets the order of KYC checks (supplemental example)
All examples are fictional.
Quiz
Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.
Pass mark: 5 of 6 questions. Q6 counts as correct at 4 of 5 rubric points. Calculated answers are accepted within ±5% of the key.
Q1 · Airline MRO · The elements, and what must stay
Scenario: A fictional overnight line station writes down its wheel and brake change as nine steps in a set order, from chocking the gear to recording the work, and agrees a five-item handover for every aircraft. The team wants to save time.
Question: Which element are the nine steps and the handover, and which step must stay even though it adds time?
Answer: B
Why:
A) Takt is the pace demand sets, not the steps.
B) ✓ The steps, in order, with their checks, are the work sequence. Required checks and sign-offs, like the duplicate inspection, are steps in the sequence, never extras to cut.
C) Standard WIP is how much may wait between steps (here, one parts kit).
D) Meeting takt never means removing a required check. In the example, staging the parts kit saves the time instead.
Q2 · Healthcare · Where is the imbalance?
Scenario: A fictional outpatient clinic must see 32 patients in a 480-minute session, so takt is 15 minutes per patient. Each consultation averages 9 minutes, and turning the room round for the next patient (clearing, cleaning, restocking) takes another 9.
Question: Where is the imbalance, and what does it cost over the session?
Answer: B
Why:
A) Consultation is clinical time the standard doesn't shorten; the room cycle as a whole is what runs over.
B) ✓ 9 + 9 = 18 minutes per room cycle, 3 over takt; 3 × 32 = 96 minutes across the session. A standard room reset (turnover 9 → 6) brings it to takt.
C) Each part is under takt, but the room isn't free again until both are done.
D) The overrun repeats with every patient, so it adds up over the session.
Q3 · Manufacturing · Bottleneck and people
Scenario: A fictional four-station assembly cell has a takt of 112.5 seconds. The stations' cycle times are S1 95 s, S2 130 s, S3 88 s and S4 105 s.
Question: Which station is the bottleneck, and how many operators does the cell need?
Answer: B
Why:
A) S3 is the shortest station: it has idle time, not a bottleneck.
B) ✓ S2 is over takt. Total work content 95 + 130 + 88 + 105 = 418 s; 418 ÷ 112.5 = 3.7, rounded up to 4.
C) The bottleneck is right, but 3 operators can't cover 3.7 operators' worth of work: always round up.
D) S4 is under takt, and 5 operators is more than the work needs.
Q4 · Logistics · Reading a tote pile
Scenario: A fictional fulfillment center must pack 1,800 orders in a 7-hour shift across 6 pack stations: 300 orders per station. The standard allows no more than 2 totes (plastic crates of picked items) waiting at each station. Packing averages 96 seconds per order, and one station has 5 totes waiting.
Question: What is the takt per station, what's the gap, and what does the tote pile tell you?
Answer: A
Why:
A) ✓ 7 h = 25,200 s ÷ 300 = 84 s. At 96 s each order runs 12 s over, so totes pile beyond the 2-tote standard: the pile shows the problem the moment it starts. Look at the steps, not the person.
B) 96 s is the cycle time, not takt.
C) The figures are right, but blaming the person misses the point: fix the work and the instruction.
D) The takt is wrong, and raising the WIP limit would only hide the pile-up.
Q5 · Banking/Services · Transfer question
Scenario: A fictional bank's KYC team ("know your customer": checking a new customer's identity documents) receives 240 cases a day. Six reviewers share the work equally, and each has 6.5 productive hours (390 minutes) a day.
Question: What is the takt per case for each reviewer?
Answer: B
Why:
A) This is 390 minutes ÷ 240 cases: the whole team's demand against one reviewer's time.
B) ✓ Each reviewer gets 240 ÷ 6 = 40 cases a day: 390 ÷ 40 = 9.75 minutes per case. (Equivalently, 6 × 390 = 2,340 reviewer-minutes ÷ 240 cases.)
C) This is 390 ÷ 10: the wrong demand.
D) This is 390 ÷ 6: time per reviewer, not per case.
Why this transfers: banking isn't planned for M8, and the scenario explains its term (KYC). A learner who can divide available time by demand can answer without banking knowledge.
Q6 · Writing exercise (learner's choice)
Task: Write a standard work instruction for a task you do often, or for this one: setting up a meeting room for a 10-person workshop (tables, screen, video call, materials, refreshments). Use the template: step · key point · reason. Then give it to someone who hasn't done the task and watch them follow it.
Rubric (1 point each; pass at 4 of 5):
#
Point awarded when…
1
There are 5–10 steps, in order, each starting with a verb
2
Each step has a key point (how to do it right)
3
Critical steps have a reason (why it matters)
4
Required checks are written as steps (e.g. "Test the video call before people arrive")
5
A new person could follow it alone, with no questions (or the learner reports the first-try test and the fix it led to)
All examples are fictional.
Cookies on InLine Ops. We'd like to use optional analytics cookies to see how the site is used and improve it. They're only set if you accept. Read more about cookies
ACADEMY · IN PRODUCTION
The Academy opens soon
We use your email only to tell you about this. See our Privacy Policy.