The best way so far, written down

Standard work is the current best way to do a job, written by the people who do it, so anyone can do it the same way. It's the baseline you improve from, not a cage.

Element Ask How
Takt What pace does demand set? Takt = available working time ÷ demand (same units). Compare each cycle time with takt on a bar chart
Sequence What are the steps, key points and reasons? 5–10 steps in order; each with a key point (how) and a reason (why); required checks and sign-offs are steps
Standard WIP How much may wait here? A small, fixed amount in a marked place, so a pile-up shows at once

Bars vs takt: a bar over the line is the bottleneck (work piles up behind it); a bar far under it is idle time. Move work from tall bars to short ones until each is under takt. Minimum people = total work content ÷ takt, rounded up.

Instruction template

# Step Key point (how) Reason (why) Picture
1 What to do, starting with a verb The one thing that makes it right Safety, quality or ease Optional

The first-try test: give the instruction to someone new. Can they follow it alone, with no help and no errors, first time? If not, fix the instruction, not the person. When the work improves, update the standard (v1 → v2).

Watch out for: confusing takt with cycle time · writing the standard without the people who do the work · leaving required checks out · treating the standard as fixed forever.

Examples

Industry Takt Cycle vs takt Sequence and WIP
✈ Airline MRO 450 min ÷ 9 aircraft = 50 min 58 min per check; staging the parts kit cuts rectification 20 → 12 min: 50 min. Records and release untouched 9-step wheel and brake change (duplicate inspection kept) · 5-item handover · WIP: 1 parts kit, next aircraft only
✚ Healthcare 480 min ÷ 32 patients = 15 min 9 + 9 = 18 min room cycle (≈ 96 min over per session); room reset cuts turnover to 6: 15 min 6-step room reset · SBAR bedside handoff · WIP: 1 patient per room. Supports clinical judgement, never overrides it
⚙ Manufacturing 54,000 s ÷ 480 units = 112.5 s S2 130 s over takt; moving the 20 s label task to S3 puts every station under. 418 ÷ 112.5 = 3.7 → 4 operators 8-step S3 standard · WIP: 1 unit per marked square
📦 Logistics 25,200 s ÷ 300 orders = 84 s per station Observed 96 s: 12 s over takt 6-step picture instruction · WIP: max 2 totes per station (supplemental example)
🏦 Banking/Services 390 min ÷ 40 cases per reviewer ≈ 9.75 min per case n/a A standard checklist sets the order of KYC checks (supplemental example)

All examples are fictional.

Quiz

Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.

Pass mark: 5 of 6 questions. Q6 counts as correct at 4 of 5 rubric points. Calculated answers are accepted within ±5% of the key.

Q1 · Airline MRO · The elements, and what must stay

Scenario: A fictional overnight line station writes down its wheel and brake change as nine steps in a set order, from chocking the gear to recording the work, and agrees a five-item handover for every aircraft. The team wants to save time.

Question: Which element are the nine steps and the handover, and which step must stay even though it adds time?

Q2 · Healthcare · Where is the imbalance?

Scenario: A fictional outpatient clinic must see 32 patients in a 480-minute session, so takt is 15 minutes per patient. Each consultation averages 9 minutes, and turning the room round for the next patient (clearing, cleaning, restocking) takes another 9.

Question: Where is the imbalance, and what does it cost over the session?

Q3 · Manufacturing · Bottleneck and people

Scenario: A fictional four-station assembly cell has a takt of 112.5 seconds. The stations' cycle times are S1 95 s, S2 130 s, S3 88 s and S4 105 s.

Question: Which station is the bottleneck, and how many operators does the cell need?

Q4 · Logistics · Reading a tote pile

Scenario: A fictional fulfillment center must pack 1,800 orders in a 7-hour shift across 6 pack stations: 300 orders per station. The standard allows no more than 2 totes (plastic crates of picked items) waiting at each station. Packing averages 96 seconds per order, and one station has 5 totes waiting.

Question: What is the takt per station, what's the gap, and what does the tote pile tell you?

Q5 · Banking/Services · Transfer question

Scenario: A fictional bank's KYC team ("know your customer": checking a new customer's identity documents) receives 240 cases a day. Six reviewers share the work equally, and each has 6.5 productive hours (390 minutes) a day.

Question: What is the takt per case for each reviewer?

Q6 · Writing exercise (learner's choice)

Task: Write a standard work instruction for a task you do often, or for this one: setting up a meeting room for a 10-person workshop (tables, screen, video call, materials, refreshments). Use the template: step · key point · reason. Then give it to someone who hasn't done the task and watch them follow it.

All examples are fictional.