7 min video with captions · one-page job aid · short quiz
Job aid
Follow one item, find the waits
A value stream is every step one item goes through, from the customer's request to delivery, whether or not the step adds value. A value stream map shows where the work happens, where it waits, and how long each takes.
Symbols: process box (one step) · data box under it (process time) · ▲ inventory triangle (work waiting, and for how long) · dashed push arrow (work pushed on) · thin line from the top (information flow: orders and signals) · timeline ladder (waits on the upper level, process times on the lower).
How to map
Pick one item (a part, an order, a case) and one start and end point.
Walk the flow. Follow a real item; don't map from memory.
Time each step and each wait in calendar time, nights included.
Draw the boxes, triangles, arrows, information flow and timeline.
Do the sums: lead time = all process times + all waits · PCE = process time ÷ lead time. Example: 2 h of work in a 48 h lead time ≈ 4%.
Future state: find the longest waits and ask why each exists. Remove at least three sources of waste, keep every required check, list the changes needed, and recalculate.
Watch out for: mapping from memory · mixing calendar and working hours · mapping several products at once · speeding up the work instead of the waits.
Examples
Industry
Item followed
Lead time · PCE now
Future state
✈ Airline MRO
One hydraulic pump, removal to serviceable stock
179.5 h · 6.4%
Daily shuttle, pull signal, certify at test → 47.5 h · 24%
⚙ Manufacturing
One drive-shaft order, order entry to shipping
199 h · 3.5%
FIFO lane, inspect in the cell, ship daily → 103 h · 6.8%
📦 Logistics
One inbound trailer, unloading to put-away
28 h · 7.1%
Labels from the ASN, check and label in one step, pull put-away → 9.5 h · 18%
🏦 Banking/Services
One mortgage, application to funding
490.5 h · 2.1% (calendar)
Document checklist at application, valuation ordered with underwriting
All examples are fictional.
Quiz
Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.
Pass mark: 5 of 6 questions. Q3 and Q5 are marked correct within ±5% of the answer key; Q6 is marked with its checklist.
Q1 · Airline MRO · Future state
Scenario: A fictional hangar's repair loop for a hydraulic pump takes 179.5 hours from removal to serviceable stock. Only 11.5 hours of that is work. The waits are 2 days for shipping to the shop, 4 days in the queue for the repair bench, and 1 day waiting for certification.
Question: Which set of three changes belongs on the future-state map?
Answer: B
Why:
A) The work is only 11.5 of 179.5 hours. Saving an hour of it barely changes the lead time; the waits are where the time goes.
B) ✓ Each change attacks one of the three waits, and certification still happens.
C) Certification is a required check. The future state can move it or remove the wait before it, but never skip it.
D) Bigger batches make the shipping wait longer, not shorter.
Q2 · Manufacturing · Reading a map
Scenario: A fictional machine shop maps one order for a drive shaft. On the map, the box "Order entry" has "0.5 h" under it. Next comes a triangle labeled "3 d", then a dashed arrow to the box "Saw cutting". A thin line runs from "Sales" along the top of the map, with drops into each box.
Question: What does the triangle labeled "3 d" show?
Answer: C
Why:
A) Process time is in the data box under the step (0.5 h). The triangle isn't work.
B) The dashed arrow shows work being pushed on; it doesn't count anything.
C) ✓ A triangle is inventory: work waiting, and the label says for how long.
D) The thin line from Sales is the information flow. The triangle isn't part of it.
Q3 · Logistics · Calculate lead time and PCE
Scenario: A fictional distribution center follows one inbound trailer from unloading to put-away.
Step
Process time
Wait after
Unload
0.5 h
6 h
Receiving check
0.75 h
12 h
Labeling
0.25 h
8 h
Put-away
0.5 h
—
Question: Work out (a) the total process time, (b) the lead time and (c) the process cycle efficiency (PCE).
Leaving the waits out of the lead time (lead time = 2 h, PCE = 100%).
Dividing lead time by process time (14), instead of process time by lead time.
Counting only the longest wait.
Q4 · Banking/Services · Calendar time vs working hours
Scenario: A fictional lender maps one mortgage from application to funding. Work adds up to 10.5 hours, and the case waits 20 calendar days between steps. The lead time is 490.5 hours, so the PCE is about 2.1%. A colleague counts only working hours (8 hours a working day, about 14 working days of waiting) and gets a PCE of about 9%.
Question: Which statement is right?
Answer: C
Why:
A) Nothing in the process changed; only the way the waits were counted.
B) 2.1% is correct for calendar time.
C) ✓ Both are valid sums. Value stream maps use calendar time because that's what the customer waits.
D) The customer's wait doesn't stop at night or at weekends, even if work does.
Colleague's sum (for the marker): 14 working days × 8 h = 112 h of waiting, so lead time = 122.5 h and PCE = 10.5 ÷ 122.5 ≈ 8.6%.
Q5 · Healthcare · Transfer question
Scenario: A fictional hospital follows one outpatient MRI scan, from the referral to the report reaching the referring doctor. An MRI is a type of body scan; the radiologist is the doctor who reads it.
Step
Process time
Wait after
Booking the scan
0.25 h
10 days
The scan
0.75 h
2 days
The radiologist writes the report
0.5 h
1 day
The report is sent
0.1 h
—
Question: Work out the lead time in hours and the PCE. Count each day as 24 hours.
Answer: Process time = 1.6 h · Waiting = 13 days = 312 h · Lead time = 313.6 h · PCE = 1.6 ÷ 313.6 ≈ 0.5%. Accept 298–329 h and 0.48–0.54% (±5%).
Why this transfers: healthcare isn't in this module's video, and the scenario explains every step, so a learner who can do the sums on any map can answer it.
Q6 · Build exercise · Current-state map
Task: Draw a current-state value stream map, with a timeline, for this fictional mortgage process. The lender's case system tells each team which case to work on next.
Step
Process time
Wait after
Application intake
1.0 h
3 days
Document check
2.0 h
5 days
Underwriting
4.0 h
4 days
Valuation review
1.0 h
6 days
Offer and closing prep
2.0 h
2 days
Funding
0.5 h
—
Checklist (pass at 4 of 5 points):
Six process boxes in order, each with its process time in a data box.
Five inventory triangles, each with its wait.
Information flow from the case system to the steps, drawn separately from the work flow.
A timeline ladder: waits on the upper level, process times on the lower.
Correct totals: process time 10.5 h, waiting 480 h, lead time 490.5 h, PCE ≈ 2.1% (±5%).
All examples are fictional.
Cookies on InLine Ops. We'd like to use optional analytics cookies to see how the site is used and improve it. They're only set if you accept. Read more about cookies
ACADEMY · IN PRODUCTION
The Academy opens soon
We use your email only to tell you about this. See our Privacy Policy.