ACADEMY · FREE MODULE 1 OF 11

M1 · Intro to Process Improvement

6 min video with captions · one-page job aid · short quiz

Job aid

Process, customer, value, waste

Process: a series of steps that turns inputs into outputs for a customer. Customer: whoever receives the output, inside the organization or outside it. Value: what the customer would willingly pay for. Waste: anything else that uses time, effort or money.

Is this activity… Ask Then
Value-adding Does the customer care? Does it change the product or service? Is it right first time? Protect it
Waste No to any of those, and nothing requires it Remove it
Required No value to the customer, but safety or regulation demands it Keep it; make it easier

SIPOC: Suppliers → Inputs → Process (5–7 high-level steps) → Outputs → Customers. Fill in C first, then work backwards.

Lean Six Sigma
Asks Why is this slow? Why is this different every time?
Works on Flow: removing waste Variation: using data to cut defects

Watch out for: calling required steps waste · listing steps before naming the customer · treating Lean and Six Sigma as rivals (most teams use both).

Examples

Industry Example
✈ Airline MRO Hangar check. Customer: airline operations. Lean removes walks to stores; Six Sigma cuts the 6% of task cards returned for missing entries. Duplicate flight-control inspection: required.
✚ Healthcare Knee procedure. Customer: patient, family, GP. Lean cuts the 2 h pre-op wait; Six Sigma cuts the 4% of procedures cancelled for a missing test. Consent: required.
🏦 Banking/Services Account opening. Customer: the applicant. Lean removes re-keying; Six Sigma cuts the 8% of applications failing ID matching. KYC check: required.
⚙ Manufacturing Bracket line. Customer: an equipment assembler. Lean shortens the 9-day wait before paint; Six Sigma cuts the bend-angle variation behind 3% rework.

All examples are fictional.

Quiz

Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.

Pass mark: 4 of 5 questions. Q1 counts as correct at 8 of 10 items; Q5 is marked with the rubric.

Q1 · Airline MRO · Sort ten activities

Scenario: A fictional regional hangar is running a scheduled A-check. The customer is the airline's operations control, which needs the aircraft back on time and airworthy.

Question: Mark each activity V (value-adding), W (waste) or R (required: no direct value, but safety or regulation demands it). You need 8 of 10 correct.

# Activity Your answer
1 Inspecting a landing gear
2 Replacing a worn brake
3 Walking to stores for a seal
4 Waiting for an engineer's sign-off
5 Re-printing a lost task card
6 Duplicate inspection of the flight controls
7 Moving the aircraft between bays
8 Searching for a torque wrench
9 Lubricating hinges
10 Entering the same data in two systems

Q2 · Healthcare · SIPOC

Scenario: A fictional community hospital is drawing a SIPOC for a planned knee procedure, from GP referral to discharge.

Question: Which item belongs in the Inputs column?

Q3 · Banking/Services · Lean or Six Sigma

Scenario: At a fictional retail bank, two problems slow down account opening:

  1. Staff re-key every paper form into the core system.
  2. About 8% of applications fail ID matching, and the failures come from inconsistent data entry.

Question: Which pairing fits best?

Q4 · Manufacturing · Transfer question

Scenario: On a fictional steel-bracket line, the steps are cut → bend → weld → paint → pack. Welded brackets sit for about 9 days before they're painted, and nothing happens to them in that time. The customer is an equipment assembler.

Question: How should the 9 days between welding and paint be classified?

Q5 · Written answer · Lean and Six Sigma

Question: In three to five sentences, explain how Lean and Six Sigma differ, and how they work together. Name at least two differences.

All examples are fictional.