One road map for improvement projects
DMAIC has five phases. Each phase answers one question. You can loop back when you learn something new, but don't skip a phase. Write a charter before you start.
Phase
Key question
Typical tools
Done when
D Define
What's the problem, for whom, and what does good look like?
Charter · SIPOC · voice of the customer
The sponsor signs the charter
M Measure
How big is it now, and can we trust the data?
Baseline · data collection plan · process map · run chart
Pilot · 5S · standard work · mistake-proofing · kaizen event
A pilot meets the goal; required checks stay
C Control
How do we keep the gain?
Control plan · control chart · huddle board · leader standard work
An owner checks the measure on a set schedule
Some tools fit more than one phase (a run chart measures the baseline and later watches the gain).
Charter checks, one per field
Field
Check
Problem
What, where, when, how much against a baseline. No cause, no blame, no solution
Goal
A number and a date
Scope
What's in and what's out
Team
A sponsor, a lead and the people who do the work
Timeline
A date range for each phase
Watch out for: a solution hidden in the problem statement · skipping Measure because "we already know" · a goal with no date · leaving Control to chance.
Examples
Industry
Problem
Goal
Main tools
✈ Airline MRO
A-check TAT 11.2 h vs 10.0 h window; 4–6 late departures a month
≤ 9.0 h and ≤ 1 late departure a month by end of Q3
Time stamps · Pareto (parts not ready 46%) · pre-kitting · run chart. Result: 8.9 h over 15 checks
✚ Healthcare
30-day heart-failure readmissions 21% vs a 16% benchmark (both invented)
≤ 17% within 9 months
Checklist data · fishbone · teach-back and 72 h call · run chart. Result: 18% after 4 months
📦 Logistics
Store-delivery OTIF 91% vs a 97% agreement
≥ 96% within 6 months
Late/short reasons · Pareto (late trailers 55%) · loading windows · OTIF chart. Result: 96.4% over 8 weeks
⚙ Manufacturing
Bracket-line scrap 3.1%
1.5% within 5 months
Scope: bending and welding (supplemental example)
🏦 Banking/Services
Complaint resolution 18 working days
10 days within 6 months, holding satisfaction
Scope: written retail complaints (supplemental example)
All examples are fictional.
Quiz
Answer each question first; the answer and why open after you choose or press “Show the answer”. Nothing is saved or sent.
Pass mark: 5 of 6 questions, and Q4 must reach 8 of 10. Q6 counts as correct at 4 of 5 rubric points.
Q1 · Airline MRO · A well-written goal
Scenario: At a fictional hangar, overnight A-checks take 11.2 hours on average against a 10.0-hour window, and 4–6 departures a month leave late. The team is writing the goal for its charter.
Question: Which goal is best written?
Answer: C
Why:
A) No number and no date: nobody can tell when it's met.
B) A number, but no date.
C) ✓ A number and a date, for both the turnaround and the late departures.
D) It names a solution before Analyze has found the cause.
Q2 · Healthcare · Which phase?
Scenario: A fictional cardiology ward's project team has a signed charter. They are now pulling 30-day readmission figures and checking how often the discharge checklist is actually completed. They haven't looked at causes yet.
Question: Which phase are they in, and what question are they answering?
Answer: B
Why:
A) The charter is already signed, so Define is done.
B) ✓ They're setting a baseline and checking the data before looking for causes.
C) Analyze comes next, once the data is trusted.
D) Nothing has been changed yet, so there's no gain to keep.
Q3 · Logistics · Tool and phase
Scenario: A fictional distribution center (DC) delivers to 40 stores. Every missed delivery has been coded by reason, late or short. The team now ranks the reasons from biggest to smallest and finds that late trailer departures cause 55% of misses.
Question: Which tool did they use, and in which phase?
Answer: C
Why:
A) A run chart shows a measure over time, not reasons ranked by size.
B) A SIPOC maps the process at a high level; it doesn't rank causes.
C) ✓ A Pareto chart ranks causes so the team can focus on the few that matter most: an Analyze job.
D) Nothing is being tried yet; they're still finding the cause.
Q4 · Tool-mapping exercise (mixed industries)
Task: Place each tool in the phase where it's mainly used: Define, Measure, Analyze, Improve or Control.
Project charter
Fishbone diagram
Control plan
Baseline
Pilot
Voice of the customer
Pareto chart
Data collection plan
Huddle board
Standard work
Answer key (1 point each; pass at 8 of 10): 1 Define · 2 Analyze · 3 Control · 4 Measure · 5 Improve · 6 Define · 7 Analyze · 8 Measure · 9 Control · 10 Improve.
Also accept: standard work in Control, if the learner explains it holds the gain (M11 uses it this way).
Q5 · Banking/Services · Transfer question
Scenario: A fictional retail bank's complaints team drafts this charter:
Problem: written complaints take 18 working days to resolve (a working day excludes weekends and holidays).
Goal: 10 working days within 6 months, while holding the customer satisfaction score.
Scope: in: written complaints in retail banking; out: phone complaints and business banking.
D) ✓ No sponsor and no team are named, so nobody owns the project.
Why this transfers: banking isn't planned for M6, and the scenario explains its one term (working day). A learner who knows the five charter fields can answer without banking knowledge.
Q6 · Charter exercise (learner's choice)
Task: Write a one-page charter for a problem you know, or use this case: a team's monthly invoices go out on day 9 of the month on average; customers expect them by day 5, and late invoices delay payment.
Rubric (1 point each; pass at 4 of 5):
#
Point awarded when…
1
The problem has what, where and how much against a baseline or expectation, with no cause or solution in it
2
The goal has a number and a date
3
The scope names what's in and what's out
4
The team names a sponsor and the people who do the work
5
The timeline gives a date range for each of the five phases
All examples are fictional.
Cookies on InLine Ops. We'd like to use optional analytics cookies to see how the site is used and improve it. They're only set if you accept. Read more about cookies
ACADEMY · IN PRODUCTION
The Academy opens soon
We use your email only to tell you about this. See our Privacy Policy.